Client
Jammie's Environmental
Type of Project
Services Performed
Market
Commercial
Duration
3 Months
After a devastating flood in 2021, our teams worked around the clock to rebuild and repair the Sumas Railroad.
We performed a removal of 20,000 yds of flood deposit, imported 3,000 tons of rail ballast and 2,000 tons of riprap (rock), and fine-graded and prepped 6,000 ft for the installation of new rail and rail alignment.
All work was performed for the main contractor on this project, Jammie's Environmental.