Skip to main content
Edit Page Style Guide Control Panel

Client

Sierra Pacific

Type of Project

Services Performed

Market

Commercial

Duration

5 Months

A large project consisting of asphalt grinding, patching, and paving for Sierra Pacific.

The asphalt repair project at Sierra Pacific kicked off in November 2023 and finished in April 2024. There were two mobilizations for this project and the work was to be completed only on the weekend when the plant was shut down. 

The paving team completed a large asphalt grind and multiple areas of asphalt patching. The log yard in Burlington on McFarland Rd was also paved completely during this project. 

Our Asphalt team laid down approximately 1,600 tons of asphalt mix. To wrap up, our Sealcoating team came in to perform crack sealing.